A can do a piece of work in 40 days
Asked by admin @ in Math viewed by 301 People
X can do a piece of work in 40 days. he works at it for 8 days and then y finished it in 16 days. how long will they together take to complete the work?
a. 13 1/3 days
b. 15 days
c. 20 days
d. 26 days